FERGUSON Marine yesterday announced the completion of a major milestone in the build of one of the dual fuel ferries currently under construction.

Hull 802, as the vessel is currently known, was fitted with its large bow unit which is the largest single unit added to the ferry’s steel hull, completing the bow structure.

This week will mark a key moment in the vessel’s progress when the final units are lifted into place, completing the main hull and steelwork and making way for the installation of

the ferry’s aluminium superstructure, which is all the units that sit above the main deck.

The National: Night time view of a vessel under construction at the Ferguson Marine shipyard at Port GlasgowNight time view of a vessel under construction at the Ferguson Marine shipyard at Port Glasgow

Over the coming weeks and months, resources will ramp up to around 150 people working on Hull 802 to support the construction effort.

David Tydeman, CEO of Ferguson Marine in Port Glasgow, said: “Later this week, we will install the final steel block, which will complete the main hull on the vessel.

“We will then implement a step change in momentum behind the build of Hull 802 with increased resources over the coming weeks and months to install the units which sit above the main deck.

“One of the key changes I have made since taking over is separating the programmes for the two dual fuel vessels.

The National: The 100-tonne block lift of the bow to be connected onto Hull 802The 100-tonne block lift of the bow to be connected onto Hull 802

“This is to allow the programme for vessel 802 to progress, irrespective of the schedule and programme for MV Glen Sannox. This approach will allow us to work towards launch early next year. My aim is to demonstrate that Ferguson Marine, in line with its historic reputation and without legacy issues, has the capability to deliver a new-build vessel.”